Champion Lakes – Early Learning Centre

CONSTRUCTION STARTED – CHAMPIONS LAKES

Sometimes you just need to take a deep breath and review the project design during these cost crazy times.

Harrper Projects was engaged to value manage this 88-licensed early learning centre development in Champion Lakes. A significant redesign of the previously approved DA roof structure was identified that could produce cost savings (see comparison renders below).

Also, several external wall elements were workshopped with our D&C building contractor IQ Construction to achieve time and cost savings without compromising the integrity or aesthetic of the project.

An ECI contract was entered into while an amended Development Application was submitted and subsequently approved.

Footings, slabs, and drainage have been constructed & installed during the design and DA approval period with bricklaying commencing shortly. Project completion is scheduled for June 2025.

Great job team!